In the area of cost prediction
and financial analysis the same issues with OEM and third party provision of
information exist as in production information. The bottom line is
financial analyses are regularly not delivering the right answer for appropriate
decision making. In most cases production estimates are higher than what
is achieved and cost estimates are lower. I previously asked the
question, is it a human trait to be optimistic or is it pressure to produce
results which are good enough to gain shareholder or Executive Management
approval? I suspect it is a combination of both. The issue I
identified last blog about the continual challenge to turn mineral deposits
into a financial return is not easy. If the mine plan says it is not
economic then shareholder money is wasted and employees don’t have a job.
We in the mining industry live in hope that something will change. About
every 25 years they do (and it lasts for 6-8 years) but there is an
unmistakable longer term downward trend in commodity prices.
Through the last resource
downturn (1985 – 2002) we saw mines start with fanfare and substantial capital
spent. Eventually owners lose patience and look for a buyer /
partner. One from overseas who has no specific knowledge of the industry
is always good because you can make ambitious predictions on future prices with
no real basis for an expectation that they might be accurate. The classic
example of this was when Agipcoal purchased 25% of the MIM NCA coal mines in
the late 1980’s. Here you had two mines (and a port) which were running
at an operating loss less than ten years after MIM had spent hundreds of
millions of dollars building a mine and upgrading another. The financial
predictions of future costs and income were simply never achieved and Agipcoal
did not remain as a long term owner. What happens is that assets change
hands at lower and lower prices until someone can make money or the mine is
closed or we simply wait long enough for the prices to turn.
So who is responsible for the
cost (and income) predictions. Each of the major mining consultants will
tell you they have the cost data for all the major equipment. But my
question is where does it come from as it often bears no relationship to
reality. Those that do bear some relationship to reality - well who
actually owns the data? There is a bigger problem here. Cost
allocation, reporting and control is done very badly by a large number of the mines
around the world. While the quality of production monitor output is
reasonably consistent and is getting better I am aghast at the quality of
financial control. When a cost benchmark is done it takes 2-3 weeks on
site to access the data and put it into a format which is firstly credible and
secondly can be compared with others. This makes the quality of financial
analysis on a mine very dubious because very few people have the time to get
the data into an appropriate form. In the majority of cases the cost of
an individual piece of equipment is (much??) higher than what the mine thinks
it is. So the situation evolves whereby people on the mine have a very
poor idea of cost and they seek confirmation from others of costs.
Unfortunately they often turn to mining consultants and suppliers of
equipment. Mines seem to think that just because they do it badly most
others must do it well so consultants and suppliers must know equipment
operating costs. Wrong!!! For starters suppliers have a vested
interest in telling you low costs and consultants have a vested interest in
making the economics look good to continue to further studies. Both
groups readily use low cost data.
Apart from the poor financial
control demonstrated by most mines, the following are actual reasons why overly
ambitious (low) costs have been used (some are mine and some have been provided
by Rob Beckman of Red Button group);
- The data that is used can be
many years old and does not include appropriate escalations,
- The costs can simply be wrongly
estimated, taken from a small sample of cost that is not the long term
average,
- The cost is often gained from
contract prices that are only a subset of total cost of the assets,
- There is no consideration of
duty cycle which as a dominant factor in the cost of the equipment (eg.
Steep grades, ripping for dozers, double benching for excavators etc etc)
- Finally, the costs are a $/hr
average in most cases which do not take into account the lifecycle
variation of equipment cost. The cost of a single piece of equipment
will vary by 50% from year to year depending on the work that is done and
it can be shown that even over very large fleets this does not average out
year to year.
In my next blog I will provide
some examples of costs which were provided by a number of mine planning
consultants and were just simply wrong.
Graham Lumley
BE(Min)Hons, MBA, DBA, FAUSIMM(CP), MMICA, MAICD, RPEQ
No comments:
Post a Comment