This blog I want to present a
case study where a mine had a large shovel with 44 CuM dipper loading 218 tonne
trucks perfectly in two and a half passes! (Situation normal for most!)
The dilemma, faced by multitudes of mines around the world, is do you put a
third small pass in the truck or do you send it away 80% full?
The average payload of the
shovel was 85 tonnes. The original methodology for determining the match
was not known but the performance of the dipper was quite good when looking
around the industry. It appears likely that the original aim was to fill
the 218 tonne trucks in three passes. Two passes sent trucks away with an
average of 170 tonnes payload. The decision was made not to put the third
pass into the trucks due to the loss in productivity, damage caused to trucks
by overloading and the increased spillage.
The desired average payload was
218 tonnes per truck (109 tonnes per dipper). The mine had a quote from
the OEM to change the boom geometry of the two shovels and provide two new
dippers. Quote was for $6M+.
Using a combination of data
analysis and physical modelling four stages of work were undertaken with the
following outcomes;
Stage
1 Analyse data. Process changes
recommended. Discussions held with operators.
Result - Payload
increased to 95 tonnes on average which was in line with best practice dipper
performance.
Stage
2 Physical modeling of the
existing dipper, the supplier’s recommended dipper and two boom geometries.
Result – Modelling
proved accurate. Modelling demonstrated under-performance of supplier’s
recommended dipper relative to existing dipper. Recommendation made not
to change boom geometry. Recommendation not to purchase new dipper due to
substantial under-performance. Recommendation to test changes to existing
dipper.
Stage
3 Physical modeling of changes
to the dipper.
Result – A number
of changes had a positive impact on payload but none gave enough by themselves
to increase payload to 109 tonnes. Recommendation to conduct further testing
combining various options to modify the dipper.
Stage
4 Four options were presented
which met the target 109 tonne average
payload,
(Figure 1).
The mine chose the preferred
option with a slight change, engaged a structural engineer to design the
modifications and a local business undertook the modifications to one dipper
(Figure 2).
End Result
All up cost $350,000, Average Payload 111 tonnes. Value to mine at the time $8M
per annum.
Consequently a second dipper
was modified for the second shovel.
All up cost was $470,000 with
two dippers achieving 111 tonnes and 109 tonnes average payload. Cash saved on
the project >$5.5M. Value to the mine $15M per annum.
The most important lesson here
is that you can’t achieve anything if you won’t have a go. The four
stages here took 18 months and were rigorously evaluated before proceeding, but
the key is that they did it and they added real value.
No comments:
Post a Comment